Cases

Concept Study for HVAC Platform Closed Deck vs. Open Deck

Written by Semco Maritime | Aug 1, 2024 10:00:00 PM

Customer: ConfidentialLocation: EuropePeriod: 2024

The solution

Conceptual design of an HVAC platform for harsh metocean environment. Comparing an open deck solution vs closed deck solution highlighting the technical, operational, economic and risk differences.

Competences and systems
  • High-voltage, medium voltage
  • Open deck vs closed deck topsides
  • Main & Aux. equipment
  • OSS layouts
  • Jackets and topsides costs
  • CAPEX & OPEX estimations
  • Risks analysis & evaluation
Highlights
  • Concept study was delivered within a very short time frame
  • Exploring new designs and technologies

Click here to read more about our engineering studies.