Fengmiao 1 (FEM1) OSS EPCI

Written by Semco Maritime | Jul 24, 2025 6:54:27 AM

Customer: Copenhagen Offshore Partners (COP)Location: Taiwan (off the coast of Taichung City)
Capacity: 495 MW
Period: October 2023 - February 2027

Activities
Solution

A full EPC contract covering electrical and mechanical engineering,
procurement, construction and commissioning (onshore/offshore) of
all E&I for the Feng Miao 1 Wind Farm offshore substation.

HV/MV equipment and LV/HVAC panels are novated equipment in the
start-up of the EPC phase due to localization agreements in the PPA.

Competences and systems:
Highlights
  • Semco Maritime's second offshore substation contract for the Taiwanese market
  • Semco Maritime's and PTSC M&C entered into a consortium for this project
  • The SMPTSC scope also included the supply of 50% local Taiwanese engineering hours