Maersk Developer - Offshore SPS

Written by Semco Maritime | Mar 17, 2022 2:00:00 PM

Maersk Developer SPS

Customer: Maersk Drilling
Location: Trinidad and Tobacco, The Caribbean
Period: 2021-2022

Staff arrived from Brazil, Portugal, Romania and Denmark, and we had arranged local manpower from Trinidad. +20 people are on board the rig solving multiple scopes. We have been responsible for all aspects of the project, including rig survey, fabrication of spools and structural items, installation on board the rig,  organisation of stakeholders, and last, but not least, commissioning.

Competences and systems
  • Replacement of well test lines
  • Repair of anchor winch platforms
  • Upgrade of helideck to comply with CAP437 and Brazilian standards
  • Upgrade of BOP test stump foundations and platforms
  • Various equipment and steel upgrades
  • Rig air compressor system upgrade
  • Bumper bar replacement for riser storage area
  • Subsea Knuckle Boom Crane (SSKBC) foundations and wire replacement
Highlights
  • More than 13,000 multidisciplinary man-hours offshore
  • Delivery of fabrication packages and installation materials from the US, Europe and local suppliers