Noble Resilient helideck replacement

Written by Semco Maritime | Jan 31, 2024 11:00:00 PM

Customer: Noble DrillingLocation: Skagen, DenmarkPeriod: October 2023 to April 2024

In October 2023, Semco Maritime began a fast-track project for Noble Drilling to replace the helideck on the Noble Resilient rig in Skagen, Denmark, after it was lost in an incident. The project, running until April 2024, involved the fabrication and installation of a new certified landing deck, along with firefighting, lighting, PA/GA, fire detection, and telecommunications systems. Semco Maritime's comprehensive approach included engineering, procurement, construction, and installation, ensuring compliance with HCA, ABS, and Transport Authority standards.

Solution

Following an incident in which the rig lost its entire helicopter landing deck and supporting structures, Semco Maritime was tasked with the fast-track fabrication and installation of complete replacement structures and systems. This included a new, certified landing deck, firefighting systems, lighting systems, PA/GA systems, fire detection system and telecommunications system.

Competences and systems
  • Fabrication
  • Engineering
  • Procurement
  • Logistics
  • Expediting
  • Telecommunications
  • Helideck landing lighting system
  • Fire detection
  • Firefighting
  • Piping 
  • Lifeboat installation
  • Structural and mechanical installation
  • Installation and commissioning 
  • Authority approval
Highlights
  • Over 100 structures fabricated within 60  days
  • Installation of the substructure in one piece at a new location (the first rig to be visited) during winter conditions
  • Received acceptance from HCA, ABS, and the Transport Authority.