Sandbank Offshore Substation

    

Customer

Bladt Industries

Location

Germany

Period

2014-2016

Project scope

One of the largest Semco Maritime offshore substation projects and the largest as far as the scope is concerned given that HV systems, SCADA and protection are part of this project.
The project phases include engineering, procurement, installation and commissioning of topside equipment.
The project was completed in August 2016 after which intensive testing and training will take place.
Sandbank Offshore Substation

Nordsee One

    

Customer

Bladt Industries

Location

Germany

Period

2014-2016

Project scope

EPCI contract including all electrical disciplines and all phases from design to commissioning of an offshore substation for Innogy Nordsee 1 Wind Farm. Semco Maritme’s scope include: Transformers, high voltage equipment, medium voltage equipment, F&G detection, Firefighting system, heating, ventilation and air conditioning, communication
Nordsee One