AES Nejapa Landfill Gas Power Plant 6 MW

Customer AES Nejapa Gas Ltda. de C.V.
Location El Salvador
Period 2010 
Project scope

Built in 2010, this turnkey 6,345 MW landfill power plant project included design, engineering, procurement, installation and commissioning. Fueled by methane gasses from an adjacent landfill, the plant is the first of its kind in Latin America.

Nejapa biogas power plant

Panama, Cerro Patagon

Customer Urbalia, Ethuss Group
Location Panama
Period 2015-2016 
Project scope

8.1MW bio-fuel power plant using methane gas from a landfill as fuel. The project included the 13.8kV grid connection and auxiliary equipment for drying and cleaning the gas. The 8.1MW is provided by three J620 Jenbacher engines. The project includes utilities for drying and cleaning the landfill gas. Semco facilitated and arranged funding for the project via a local bank. 

Panama, Cerro Patagon

Kenneth Jørgensen

Senior Vice President

Semco Maritime A/S

Esbjerg Brygge 30

6700 Esbjerg

Denmark

 

 

Jacob Rikard Nielsen

Regional Sales Manager

Semco Maritime A/S

Esbjerg Brygge 30

6700 Esbjerg

Denmark

 

 

Mathias Kolringen

Development and finance manager, Power projects

Semco Maritime A/S

Esbjerg Brygge 30

6700 Esbjerg

Denmark

 

General enquiries

Please contact our head office

Semco Maritime A/S

Esbjerg Brygge 30

6700 Esbjerg

Denmark