The Noble Intrepid project for Noble Corporation in Aberdeen (October-December 2023) focused on contract readiness. Building on the Noble Innovator's success, the team facilitated the rig's arrival and managed project tasks like quayside setup, procurement, and installation. Key competencies included project management, scaffolding, and compliance with CDM regulations. The client praised the team's crucial role in meeting deadlines.
Enabling access and permission to arrange the arrival of the Noble Intrepid to arrive in the Aberdeen South Harbor, using the footprint of the Noble Innovator as a basis and plan of entry. Consolidation of the Bridging Document between all parties. Arranging for the access and set up of the quayside for site inductions, welfare, and logistics
"Thank you and your team for the assistance and work completed whilst in Port of Aberdeen. Without it, we would not have made it out on time"
Click here to read more about our Shipyard In a Box services.