Cases

Vineyard Wind OSS – FAS System Design, Configuration and Commissioning

Written by Semco Maritime | Aug 30, 2021 10:00:00 PM

Customer: Vineyard
Location: Offshore USA (east coast)
Capacity: 806 MW
Period: 2021 - 2023

Activities
Solution

Delivery of a fire detection system for the OSS platform, designed in compliance with US standards and regulations. The system is capable of fire detection and provides trip and control functionality according to the C&E matrix, as well as interfacing with and controlling the fire extinguishing system (FES). 

Competences and systems:
  • System design in accordance with NFPA regulations
  • Equipment procurement 
  • Design of main control cabinet
  • Management of cabinet manufacturing
  • System configuration according to the C&E matrix
  • Factory acceptance testing
  • Harbor acceptance testing
  • Site (offshore) testing and commissioning
  • Engineers and leaders for offshore management and supervision
Highlights
  • Our second offshore wind farm project in Taiwan, including offshore substations
  • The second largest offshore substations in Taiwan