Vessel modification contract on two Cadeler windfarm installation vessels

Written by Semco Maritime | 1/23/23 8:36 AM

The scope of work comprises planning and supplier coordination as well as fabrication and installation of a new boom rest, reinforcement of the crane pedestal and various electrical and mechanical upgrades during the installation of new improved cranes supplied by GustoMSC.

Fabrication of an estimated 300 tons of steel structures will be initiated in early 2023 with planned installation on both vessels in the Port of Rotterdam from late 2023 and over a 5-month period.

“We are thrilled that Cadeler has awarded us this important assignment, and we look forward to continuing the great cooperation, which we have enjoyed on several projects in recent years. We will leverage our inhouse capabilities across disciplines in the fabrication process and subsequent installation to ensure a safe and efficient upgrade of the two vessels,” says Senior Proposal Manager, Rig & Offshore Marine, Semco Maritime, Peter Rygaard Nielsen.