Firefighting for Hornsea Project One

Customer: Bladt IndustriesEnd customer: ØrstedLocation: The UK part of the North SeaPeriod: 2016-2018


Design and EPCI of firefighting systems for offshore substation.
Transformers, auxiliary transformers and shunt reactor rooms are protected by a stand-alone foam system (fluorine-free foam). All other rooms requiring fire protection are protected by an argonite inert gas system.

Competences and systems
  • Fire alarm system
  • Foam fire extinguishing system
  • Argonite fire extinguishing system
  • Electrical design and interface
Highlights
  • Construction and installation of three (3) offshore substations for the largest wind farm in the world (1,200 MW – 2018)
  • Both systems are controlled by FAS (fire alarm system) - also designed and supplied by Semco Maritime
  • DNVGL design approved
  • Project delivered on time