Customer: Copenhagen Offshore Partners (COP)Location: Taiwan (off the coast of Taichung City)
Capacity: 495 MWPeriod: October 2023 - February 2027
Activities
Solution
A full EPC contract covering electrical and mechanical engineering,
procurement, construction and commissioning (onshore/offshore) of
all E&I for the Feng Miao 1 Wind Farm offshore substation.
HV/MV equipment and LV/HVAC panels are novated equipment in the
start-up of the EPC phase due to localization agreements in the PPA.
Competences and systems:
- Project Management
- High-voltage and medium-voltage systems
- Low-voltage systems
- Diesel generator systems
- Protection & control systems
- Fire alarm systems
- Fire extinguishing systems
- HVAC systems
- Communication & IT systems
- Platform identification systems
- Equipment, piping, ducting and HV/MV/LV cable tray system/ space management
Highlights
- Semco Maritime's second offshore substation contract for the Taiwanese market
- Semco Maritime's and PTSC M&C entered into a consortium for this project
- The SMPTSC scope also included the supply of 50% local Taiwanese engineering hours