Customer: Bladt Industries
End customer: Ørsted EnergyLocation: The German part of the North SeaCapacity: 450 MWPeriod: 2012-2013
Activities
Solution
A full electrical engineering, procurement, construction and installation (EPCI) contract covering substation for the Borkum Riffgrund 1 offshore wind farm. The project involved several electrical disciplines including low-voltage systems.
Competences and systems:
- Project management
- High-voltage and medium-voltage systems
- Low-voltage systems
- Diesel generator systems
- Protection & control systems
- Drainage and waste systems
- HVAC systems
- Communication and IT systems
- Platform identification systems
- Transport/spacing
Highlights
- Positive feedback from customer regarding general workflow and quality of work delivered
- The project was delivered on time