Customer: Hai Long 2 and Hai Long 3 Offshore Wind Power Co. Ltd
Location: Taiwan Strait, TaiwanPeriod: July 2021 - March 2026Capacity: 512 MW and 532 MW
Activities
Solution
Hai Long Offshore Wind Project has established a consortium consisting of Semco Maritime and PTSC M&C, based on a Preferred Supplier Agreement involving two offshore substations for the Hai Long 2 and Hai Long 3 projects. The substations will be positioned off the Taiwanese coast and deliver more than 1 GW of green wind energy following commissioning in 2025-2026.
Competences and systems:
- Project management
- High-voltage and medium voltage systems
- Low-voltage systems
- Diesel generator systems
- Protection & control systems
- Fire alarm system
- Fire extinguishing system
- HVAC systems
- Communication & IT systems
- Platform identification systems
Highlights
- Our second offshore wind farm project in Taiwan, including offshore substations
- The second largest offshore substations in Taiwan