Customer: Cadeler A/S
Location: Esbjerg, Denmark
Period: November 2021 - March 2022


In a project for Cadeler AS, Semco Maritime undertook a crane boom extension on the Wind Orca in Esbjerg, Denmark, from November 2021 to March 2022. The project involved installing a new 7-metre boom insert, followed by load testing and certification. Key tasks included demobilizing the crane to the quayside, constructing a habitat for cutting and welding, and conducting NDT and painting. The crane was then reinstalled, rewired, and successfully load tested, achieving recertification and third-party approval.

Competences and systems
  • Demob of crane to quayside 
  • Construction of habitat
  • Cutting existing crane 
  • Installing new boom insert
  • NDT and painting of affected areas
  • Reinstalling crane
  • Rewiring crane 
  • Load test
  • Recertification and third-party approval
Highlights
  • Construction of large habitat for cutting and welding crane boom
  • Dismounting and reinstalling crane boom on vessel 
  • Cutting out existing part and installing extension 
  • Load test following welding rewiring