Walk to Work Campaign - Tyra Future Redevelopment Project

Customer: Total E&P DenmarkLocation: The Danish part of the North Sea
Period: 2019 - ongoing

Primary scope of work including the preparation of all unmanned satellites for idle mode and installation of equipment and systems.

Competences and systems
  • Full compliance with offshore safety training
  • Onshore onboarding and certification prior to offshore mobilisation
  • Multi-skilled workers
  • SAP work package
  • PIMS mechanical completion & commissioning
  • E-vision/ECOW permits
Installation of:
  • Temporary gensets
  • Diesel tanks including valves and instruments
  • Diesel bunker systems
  • Piping spools
  • Exd interface panels
  • Line-of-sight (LOS) systems
  • Various E/I and F&G equipment incl. cables and corresponding trays
  • Nitrogen distribution
Highlights
  • +20,000 blue-collar hours, offshore
  • +4,000 white-collar hours, onshore
  • No lost-time incidents (LTIs) or safety issues so far